CTRC - The California Trolley and Railroad Corporation. Preserving the historical heritage of railroading and trolleys in the Santa Clara Valley of California.
Established in 1982, CTRC, the California Trolley and Railroad Corporation, is a 501(c)(3) non-profit organization with a mission to preserve and reflect the rich legacy of rail transportation in the Santa Clara Valley for the educational and recreational benefit of current and future generations.
The warmer temperatures probably kept most workers away today, but
the very small crew did completed a significant task. Today, we completed
extraction of the damaged front left valve cage. The objective was to remove
the cage without any additional damage. It was not a simple task. Several
small modifications were made to the set up completed last week. After
better then an hour of wrenching, the cage was clear of the cylinder. Well done
to all that helped with this task. If you are interested in details of this task,
visit the restoration site on a Saturday.
Clean up of SP 1215 continues on Tuesdays. Workers are now focusing on the right
side of the locomotive, but there are a number of items to address on the left side.
Blending Historic Trolleys with Light Rail Vehicles in San Jose, California
In 1992 Mac Gaddis made a presentation to the
American Public Transit Organization on the
blending of historic trolleys with light rail vehicles.
At the time, San Jose was an early proponent of historic trolleys running on
light rail tracks.
Perhaps as a result of Mac's presentation, several other cities now offer similar operations.
It provides interesting background on the early stages of the San Jose
Trolley Corporation, a predecessor to our current CTRC.
SP2479 Status - June 20, 2009 - Extracting the Left Front Valve Cage
J. Ezovski
Absence of several key workers has not hampered progress. All
of the necessary hardware needed to attempt extraction of the left
front valve cage is complete.
Machining of the front plate, the final component, was completed
today. The plate had to be cut to size and holes drilled to accept
threaded rod.
All components were then assembled in the valve cage.
An attempt was made to extract the valve cage, but the day's late hour forced this
task to next weekend. Hopefully an image of an intact valve cage will be forwarded
to all.
A second crew was busy cleaning and polishing the locomotive's radius rods and
combination levers. Layers of paint are carefully removed and the surface polished.
Thanks to Ron and Phil for taking on this time consuming task.
The Tuesday crew continues to make progress on SP 1215. Near all of the left side of
the boiler and frame have been cleaned and painted. Work has begun on the locomotive's
right side. The locomotive end of the tender has also been cleaned and paint applied.
Much work remains.
Thanks to all that participated!
SP1215 Cleanup
Over the last three weeks a crew has been cleaning and painting SP1215.
Over 100 person hours have so far been dedicated towards this effort.
To the right is an image of 1215 taken November 2007.
The locomotive did not look good then and had further deteriorated.
Below is an image taken today.
I am not using the terms "before" and "after" as there is still much work remaining.
Work on SP1215 will continue over the coming weeks on Tuesdays.
Here's a photo of the SP1215 in San Francisco in the mid 1950s
Ribbon Cutting Ceremony To Be Held On June 3, 2009
City of San Jose, California Trolley and Railroad Corporation and the San Jose Rotary Club Cut Ribbon on Historic Trolley Line!
A new/old trolley line running nearly a mile from the History San Jose Trolley Barn of the California Trolley and Railroad Corporation (CTRC) down Senter Road to Happy Hollow Children’s Park will be inaugurated at 11:00 AM on June 3, next Wednesday at San Jose’s Kelley Park.
This historically significant reestablishment of a trolley service along Senter Road is open to the public and will feature a ribbon-cutting by San Jose Mayor Chuck Reed, City Council members, San Jose Rotary President Bert George and other dignitaries.
This new donor-constructed and volunteer-operated service featuring free rides on the beautifully-restored historic trolley cars will serve the Happy Hollow Park and Zoo, the Leninger Center, the Japanese Friendship Garden, the Rotary Office, and History San Jose.
The free rides will be available to the public after the inauguration ceremony.
For additional media information contact CTRC President Rod Diridon, Sr. at 408 924 7561 or 408 859 4447.
SP1215 Stabilization
The CTRC (Steam team) weekday crew (Larry M, Denis M and John E) has started
the stabilization of SP1215 exterior.
This work was started the week of May 18, 2009.
The plan is to complete stabilization of the side exposed to the HSJ
parking lot first then complete the otherside of the locomotive.
We plan on reinstalling the piping, hand rails, and other items
which were removed when the engine was move to San Jose from Portola California.
In addition the cab will be weather proofed and the rest of the locomotive
will be weatherized.
Before:
After:
SP2479 Status: April to Mid May 2009
April 18
With the move complete and most site infrastructure in place,
work has resumed on the locomotive.
These past two weeks members have been installing the many components that
make up the locomotives braking system.
This may not sound like a significant task, but many of these components
are of significant weight.
Weight combined with working in the now smaller area under the
locomotive's drivers, makes this a sometimes challenging task.
The new site has brought the restoration into a more prominent view
as the locomotive is easily seen from Monterey Highway and Old Tulley Road.
Visitors to the site have been frequent and often surprised about the repairs.
April 25
The fence that will separate the restoration area from the rest of
the fairgrounds is in the process of being installed.
Task should be complete this coming week.
The fence line is between 10 and 20 feet east of our site plan,
thus giving us a bit more space for parking.
Installation of the locomotive brake system continues.
All levers, beams, brake heads and shoes are now installed.
All but three pieces of the brake safety support components are in place.
We were unable to locate two of the remaining three pieces.
One of these pieces may not have been in place when the restoration
effort began.
The missing pieces will be easily formed from 2 1/2" x 1/2" bar stock.
May 9
Removal of the locomotives valves was completed on Saturday.
There were no defects noted to the right side valve and cage assembly.
Things were not so good on the left side.
Several significant gouges were observed in the front valve cage.
One of the three damaged areas is circled in the below image.
More information is needed before repairs can begin.
Initial thoughts are to replace the cage.
While one crew was removing valves, other members worked at recovering
track ballast from the old site.
Mid May
We are starting to have visitors now that the locomotive is visible
from Old Tulley road and, if you look real hard, it can be seen
from Monterey Road.
A lady came to the site with her three little children and we issued
them little hard hats.
They felt like part of the working crew as they were escorted around
the equipment and in the caboose.
The workday crew finished and secured the between-the-container shed.
It now contains the fuel and oil as well as the riding mower and racks
of equipment.
Temporarily the side rods are stored there while bushings are created.
All the equipment from the old location has been moved to our
new location including the turntable and water tank and
a property fence now separates us.
The tender and caboose have been moved up close to the locomotive
so we almost have a "train".
All the under-the-locomotive brake components have been installed.
Two safety bars had to be fabricated.
One other bar needed to be straightened.
It probably was bent in the 1937 wreck and never repaired.
Because of our new, more visible location we now must maintain
the area outside our street-side fenced location.
But the good news is that we no longer need to mow the large acreage
that is now on the other side of the property fence line.
The steam distribution pistons have been removed.
The pistons appear to be OK but one of the internal cages has
a crack that must be evaluated and repaired.
SP2479 Progress: March 23-28, 2009
By John Ezovski
A secure storage area between two containers was completed this past week.
Work included installing gutters along the roof edge, installation of the roof,
attaching chain link fencing along the back, fabrication and installation of
double gates at the entrance.
With the storage area complete, all remaining material was removed from the
women's restroom and deep sink area. The locomotives pistons that were
stored in the men's room entrance area were moved into the outdoor shop
area.
Two and one half panels of track were leveled in preparation of the final move
of the tender and caboose.
While materials were being moved and track leveled, the small shaper/planner
received some much needed attention. Various oil lines were replaced, and
the machine tested.
In addition, grass (weeds) in and adjacent to the new site were cut.
The end of the move is here! By the end of this coming week, all remaining
CTRC equipment (exclusive of the turntable and water tank) should be within
the county designated area.
2479 Update - Feb 28 through March 21 2009
Feb 28
Muddy conditions created by heavy rain during the first part of February slowed
the relocation of CTRC material to the new site but did not stop all work.
Site improvements continued. Fairgrounds staff have spread many more yards of
base rock like material. This has allowed us to ballast and level panels of track
that the locomotive will sit. The dirt bike motorcycle course operator, located
on the fairgrounds, allowed CTRC the use of a loader for several hours this past
week. Ballast from the old site was recovered, spread and tamped under the
panels of track. Some additional ballast is needed between the ties then the
locomotive can be pulled forwarded to the new work area.
The trailer was the last large object to be moved by CTRC members. Several days of work
remain to clear the old site of a number of small items. Dry weather and identifying
a storage location are all that is necessary. On the other hand, much work remains at
the new site.
On Saturday, Feb. 28, the crew decided to take advantage of the prior week's
dry conditions with an
attempt to move organizations 40 by 20 foot double wide trailer.
Tires were installed and the
task of extracting the trailer began.
Eight years ago this trailer was positioned between trees.
(We must have never thought about having to move this trailer again.)
Those trees have grown over
the years combined with the delicate structural integrity of the trailer made
extraction a bit more difficult.
Several hours of jockeying the trailer about were expended.
The trailer was successful rotated into a direction where it
could be pulled across the field to the new location.
The trailer must now be leveled, placed back onto concrete piers and electrical installed.
Mar 7
Today's large crew and dry weather moved several tasks forward. The double wide
trailer received most of the attention. The trailer was placed back on to its concrete
piers and tires were removed.
Thanks to the generosity of Mr. Pedersen of A Tool Shed, a trench was quickly dug from
the main power panel to the trailer. Conduit and wire were laid and electrical power
restored to the trailer.
A second trench was dug from the main power panel over to the rail. A circuit
breaker panel and power outlets, mounted on 4 x 4 posts, was set into the ground.
Conduit and wire have been set into place but several small connection issues remain.
Three months have elapsed since the present phase of site consolidation began. We
are very close to being able to place all of our attention on restoration of SP 2479. All
remaining material should be relocated to the new site in the coming weeks, assuming
relatively dry weather.
Thank you Mr. Pedersen for the use of the walk behind trencher!
Mar 14
Another busy week at the restoration site.
The circuit break and outlet box adjacent to the rail was connected to the
main power source.
Compressed air was also made available at this same location.
The large rack was set into its new location and filled with pallets.
Today a significant amount of material was relocated from the old site and with
this the relocation of CTRC material to the new site is almost complete! One more
day's worth of work is all that is needed to place this task in the complete column.
By the end of the month focus will be back on the locomotive.
Mar 21
Its been another busy week at the restoration site.
The most significant event taking place today. The Saturday crew completed the
necessary track work and pulled the locomotive forward 120 feet to the location
where restoration of SP 2479 may be completed.
The week day crew has begun construction of a storage shed between two of our
containers. This shed will be a secure area for equipment previously stored in rest
rooms at the old location.
This coming week fairgrounds staff will have a crane company provide a quote to
move the turn table and water tank. To help reduce this cost, the week day crew
moved a portion of the structure that supports the large water tank. This large
support is seen in the image below to the right of the double wide trailer.
Today's crew spent most of the day clearing materials from the old site.
Finally, all CTRC materials have been removed from the field previously occupied.
The end of the move is in site!
SP 2479 Update: February. 1 - 7, 2009
This past week a 200 ampere, 3 phase, 220 volt source was connected
at the new site.
The shop was connected to this source and each machine
verified for correct operation.
While machines were being check another
crew was busy plumbing the air compressor.
With all of the electrical issues resolved, the crew turned to repairing
the panels of track that the locomotive will sit for remaining repairs.
Ballast can now be recovered from the old site and the rails leveled.
The rain that has fallen during the past two days has turned the area between
the old and new sites into a large field of mud.
Our Clark forklift is not operable in this environment.
The remaining large objects at the old site,
double wide trailer and large rack, will remain until the ground dries.
Dec. 6, 2008 marked the beginning of this stage in the move.
Much has been accomplished since that date.
In two months crews have relocated three large containers
(and contents), a 26 x 32 foot boiler tube canopy (and all the
equipment it protected), and one 225,000 pound pacific class steam locomotive.
Not bad for two months work!
The warmer temperatures probably kept most workers away today, but
the very small crew did completed a significant task. Today, we completed
extraction of the damaged front left valve cage. The objective was to remove
the cage without any additional damage. It was not a simple...
In 1992 Mac Gaddis made a presentation to the
American Public Transit Organization on the
blending of historic trolleys with light rail vehicles.
At the time, San Jose was an early proponent of historic trolleys running on
light rail tracks.
Perhaps as a result of Mac's presentation, sev...
J. Ezovski
Absence of several key workers has not hampered progress. All
of the necessary hardware needed to attempt extraction of the left
front valve cage is complete.
Machining of the front plate, the final component, was completed
today. The plate had to be cut to size and hol...
Over the last three weeks a crew has been cleaning and painting SP1215.
Over 100 person hours have so far been dedicated towards this effort.
To the right is an image of 1215 taken November 2007.
The locomotive did not look good then and had further deteriorated.
Below is a...
City of San Jose, California Trolley and Railroad Corporation and the San Jose Rotary Club Cut Ribbon on Historic Trolley Line!
A new/old trolley line running nearly a mile from the History San Jose Trolley Barn of the California Trolley and Railroad Corporation (CTRC) down Senter Road to Happy Ho...
CTRC meetings are open to members and non-members. You are welcome even if you are not a member.
We usually have a short (30 minute) discussion of status of the various projects followed by a program.
We meet inside the Santa Clara railroad station itself (you may have to slide one of the sliding doors open to find us.) In the winter be sure to bring a coat - it can be a bit cool inside the station.
Date: First Monday of each month.
Time: 7pm
Location:
Santa Clara Railroad Station
1005 Railroad Avenue
Santa Clara, California