CTRC - The California Trolley and Railroad Corporation.
Preserving the historical heritage of railroading and trolleys in the Santa Clara Valley of California.

CTRC Calendar

CTRC meetings are open to members and non-members.  You are welcome even if you are not a member.

We usually have a short (30 minute) discussion of status of the various projects.

We meet at 10am at the SP2479 locomotive restoration site in the double wide trailer.

Date: First Saturday of each month.

Time: 10am

Location:
2479 Healy Avenue
San Jose, California

Upcoming Meetings:

Regular Meetings

  2013
   June 1
   July 6
   August 3
   September 7
   October 5
   November 2
   December 7

Sponsored Links

Login Form



Welcome to CTRC

ImageEstablished in 1982, CTRC, the California Trolley and Railroad Corporation, is a 501(c)(3) non-profit organization with a mission to preserve and reflect the rich legacy of rail transportation in the Santa Clara Valley for the educational and recreational benefit of current and future generations.

Among the numerous projects underway is the restoration of Southern Pacific steam locomotive 2479.  CTRC has restored for operation a number of historic trolley cars.

A major undertaking is the creation of the San Jose Steam Railroad Museum with the focal point becoming the former six stall Lenzen Roundhouse and turntable.

 
Status - May 25, 2013

John Ezovski

Machining of rod bushings continues. Driver #2's bushing for the side rod is coming along.  All that remains of the work on the Le Blond is finishing of the bushing's flange end.  Once that work is complete, the bushing will be moved to the restoration site and grease holes will be located and drilled.  Lots of work here.

Today the right front side rod was test fit.  On initial attempt at mounting the rod, number one driver pin would not accept the rod.  This was expected.

During the week, the bushing was pressed into place and the inside diameter of the bushing measured.  The inside diameter of the bushing shrunk a considerable amount.  Dimensions of the pin were checked.  It was doubtful at the time that the pin would accept the rod.

The bushing was pushed out, machined and pressed back into place.  Rod slid onto pin, as it should, with minimal effort.

 
Status - May 18, 2013

John Ezovski

Lots accomplished yesterday.

Machining of the front, right (R1) rod bushing was completed.  Two of eight bushings are now complete.  Because of the time of day, the bushing was not pressed into the rod.  That work should be complete next Saturday.  The next bushing to be machined will be for the front side rod, main pin.

Some pad welding on firebox roof sheet was also completed.  Two areas are complete and one partially finished.  There is one more large and one small area remaining.  Next week the completed areas will be measured for thickness and Form 19's generated.

Clean up of the cab's exterior surfaces has begun.  Because the cab has sat for a very long period with primer only on the exterior surfaces, the entire exterior must be wire wheeled.  Cleaned surfaces are then covered with primer.  Paint will follow.

Thanks to all that participated.

 
SP2479 Update - March/April 2013

John Ezovski

For those that may not be aware, there is a facebook page for SP2479. We are averaging about 200 hits on each update.  The link to to the facebook page is: http://www.facebook.com/pages/Southern-Pacific-2479-Steam-Locomotive/159989580109

March 2

Repairs to the damaged sander continue.

This week the cap with the severely damaged was repaired.

After a lengthy discussion it was felt that a repair similar to that performed on the valve body was best.  The cap was mounted in lathe to cut away remaining threads.  A bushing was then machined with threads on its OD.  The Bushing was pressed into place to finish the repair.

In the attached image the repaired cap is inverted in left passage.  The repaired threads in valve body are on right.  The sand passage is heavily worn.  A sleeve can be seen inserted in the passage.  This sleeve will be epoxied in place at a later date.

March 30

Today the fourth hole requiring lead was filled in the second sander valve.  Three other holes that were filled last week were drilled.  Drilling of the fourth hole was started.

The protective coating of paint that had been previously applied to pins on the right side of drivers 1 and 3 was removed and a series of measurements taken.  The outside diameter and length of the old bushings for these pins were also measured.  Drawings will be constructed prior to any machining.

The first piece of bronze was set in place on the barn's Leblond lathe.  Machining of the first bushing could begin next week.

The heavy engine hoist has been returned to the barn.  The hoist is needed to mount rod bushing material on the Leblond.

All of the yesterday's crew spent a good portion of the day at trolley barn yesterday. In addition to work mentioned regarding 2479, several other things took place.

Bill and John Z. continue to beat on HSJ's yellow forklift.  The beast continues to quit running after about 30 minutes of operation.  I'm not sure as to the end results of their efforts.

Earlier in the week, I looked over SP1215 and found that rods and other polished metal was in need of work.  Larry and Denis spent the day on this task.  There is more to do here.

Also more grass cutting at restoration site.

April 6

After three full months of kicking repair ideas, experiments and machining, repairs to the sanders are complete!  This past week repairs to the final port were completed.

Shown to the right is the body with repaired caps.  The left port required a new lead liner.  The right port require a more extensive repair.  Sand had cut away the lead liner and a good portion of the valve body wall that held the liner.  A sleeve (bushing) was machined.  Lead was then poured to fill the sleeve.  The sleeve was drilled and then epoxied into place.  The top of the sleeve and lead liner are obscured by the gray epoxy.  Also note that there is a plug screwed into the left opening at about the 1 o'clock position in the left opening.  This plug is at the 11 o'clock position in the right opening.  The threads in this hole had been completely destroyed.  The wall was not heavy enough to support a larger plug.  The solution was to machine a plug and epoxy it into place.

This is the same valve but a side view showing new air nozzles.  Both valve bodies received these.

Boring begins on the first new rod bushing on the trolley barn's Leblond lathe.  This work will be on going for a good number of weeks except for next Saturday as projects master mechanic will be away.

Other tasks: More grass cutting. At this time of year, its a weekly task.  PM on forklifts and other equipment.

April 20

Multiple measurements of the Number 1 and 3 pins have been taken.  Measurements of the outside diameter of the old bushings have also been obtained.  One set of measurements of the rod bores for these pins is also complete.  With this data drawings are being constructed for each bushing.

Machining of the first rod bushing continues.  Inside diameter is complete.  Outside diameter is in work.  Trolley barn's LeBlond lathe is being used for all work.  Lathe is performing well.  For those wanting to see this work, the process should be under way by 10 AM most Saturdays.  Clean up begins near 3 PM.  Work is occasionally performed during the week but not on a set schedule.

Decision has been made to move the locomotive's cab back to the restoration site.  The cab has been stored under cover for a number of years behind the trolley barn.  Having the cab at the restoration site will provide work for volunteers. Yesterday the cab was loaded on to a trailer.  Trailer will be towed to site in the next one to two weeks.

Clean up of SP1215 running gear continues.

April 27

Bushing for the rod/pin on the number one driver, left side is nearly complete.  All that remains is to cut a radius on the inside diameter of the flange end to fit the pin.  Machining of the next bushing has begun.

Today most of the pipe mounted on the tender for the train brake air line was removed and inspected for wear.  It was felt that this was necessary when a large hole was found in the tender's brake line.  At least one small area requires pad welding to return this line to service.

More grass was cutting at the restoration site!

This morning the locomotive's cab was moved from trolley barn to locomotive restoration site.

Prior to any work being performed on the cab, a restoration plan must be created and approved by Art, Jack/myself.

Some time back a large quantity of fir was obtained for the cab liner. This material is at the trolley barn.  It will require some milling for use.

 
Rod Bronze Has Arrived

John Ezovski

The rod bronze has arrived.

1150 pounds of bronze arrived at the trolley barn early this afternoon (March 27).

The carton was opened for inspection with no issues found.  I took measurements of the material I could access (some of this stuff is pretty heavy!).  Numbers I obtained easily meet those provided.

The carton is now stored in the trolley barn.

 
SP2479 Status - March 23, 2013

John Ezovski

Today lead was poured into three of the four sander valve body ports.  A number of different methods were discussed as to how to create new lead liners for these ports.  Most of these ideas required significant creativity.  The final solution turns out to be the simplest: fill the hole with lead and drill out the required opening.  Three of the holes have been filled.  Next Saturday these holes will be drilled.  If the resulting sleeve is acceptable, the fourth hole will be filled and drilled.

Rod bronze should now be on order!  This week a check was mailed to the vendor.  Upon receipt of check vendor was going to begin manufacturing the required material.  Material should arrive towards the end of April.

Warmer weather and small amounts of rain require site grass/weeds be cut weekly.  Properly operating lawn equipment is rather helpful.  Site continues to look good.

 
SP2479 Progress Feb 16, 2013

John Ezovski

A bit of machining on sander valve on Bridgeport.  An attempt was made to mount valve on Leblond lathe. Issues were encounter with the plan.  Another attempt will be made next week.

Some pad welding on firebox roof sheet.  There are a number of deep gouges in the roof sheet on right side in area of cab bracket.  Pad welding of these areas began today.

Site clean up. We keep the site looking pretty good, but there is always ways to make it better.  A bunch of "detail" stuff was completed and grass cut.  Place looks good.

Progress is being made with acquiring bronze for rod bushings.  Order could be placed this week or early the following week.

 
SP2479 Saturday Feb 2

John Ezovski

Small crew Saturday Feb 2.  A couple of projects are moving forward.

Every quarter or so, the locomotive and tender are rolled to prevent corrosion from forming on the various journal surfaces.  There sufficient track to the locomotive's drivers to complete on full revolution.  Two forklifts provide the pull.  the pilot truck brakes are used to stop.

The tender's air pipe to its brake cylinder had worn through . A section of schedule 80 pipe was obtained to replace the bad section of pipe.  Inspection of the train air pipe mounted on the tender is also in need of replacement.  Any one know a supplier that would like to donate about 60 feet of 1 1/4" schedule 80 pipe?

Repairs to the one heavily worn sander has begun.  A bit of refinement is needed in the process.  Hopefully this coming weekend the first step will be complete.

Friday members of the California State Railroad Museum visited the restoration site and trolley barn.  Their primary mission was to examine the Lenzen Ave. turntable prior to disassembling their table for cleaning and repair.  The turntable located directly behind the stare museum is identical to the Lenzen table.

While at the restoration site, the group also inspected the locomotive.  During this inspection, the Jerry and Karen Lane Foundation grant was mentioned and that these funds are to be used to purchase main and side rod bronze.  Albert Di Paolo, CSRM's Restoration Specialist, mentioned a possible source for rod bronze in Stockton. He will email me with contact information.  It may be possible for the rod bronze to be obtained locally.

 
Caboose Arrives From Salinas

A caboose was hauled from Salinas to History San Jose and was coupled to SP1215.

The full story and more photos may be seen here: Caboose arrives to History Park

The caboose had been in Salinas for 19 years.

The size of the caboose dictated a somewhat roundabout route: It was transported from Salinas via highways 1, 156 onto Northbound US 101 to a bit south of Gilroy.  There it was carried on highways 25 and 152 back to 101 again to continue to History San Jose.  Various permits and police escorts were involved in the process.

Peninsula Crane and Rigging (Joe Bauer) provided the lift and Taylor Trucking provided the trucks.

 
SP2479 - Saturday, Dec 8, 2012

John Ezovski

Machining of the right side reverse shaft bushing is complete.  Today the bushing was installed.  A number of different machining processes were required to turn the $240.00 piece of bronze into the required part.  Big thank you to AJR.

Several studs were turned out to replace short studs holding the front left valve cover.  Studs were installed.

A new cover was installed on the tent frame.  The frame was relocated so that protection is provided to both forklifts.

A goodly amount of water was found in the smoke box and front coupler pin holes.  Most of the water was evacuated from both locations.  New covers were fabricated for the stack and coupler pin access hole.

Trash was collected and trash bins emptied.

 
Inaugural “Holly Trolley” rides to commemorate start of historic trolley service

The Valley Transportation Authority will roll out an historic trolley for the holiday's "Holly Trolley" service this Friday, 12/7, at 6:00 PM and until 7:00 PM at the Civic Center Light Rail Station.

On Friday, December 7, join transportation leaders and the California Trolley and Railroad Corporation (CTRC) volunteers on a “Holly Trolley” ride!  The Santa Clara Valley Transportation Authority’s (VTA) historic trolley only operates this time of year, offering free rides to the various holiday festivities in downtown San Jose. Don’t miss out on this festive ride down memory lane and a chance to learn more about the spirited volunteer effort to fund and restore all six vintage streetcars on display at the San Jose Historical Museum in Kelly Park.

When: Friday, December 7, 2012; 6 – 7pm [See note, below, for CTRC attendees]  First train departs at 6:15pm from the Civic Center Light Rail Station, 803 North First Street, San Jose.

Through the month of December, the Holly Trolley will operate on an hourly schedule every Friday from 6:30 p.m. to 10:00 p.m.; and on Saturdays and Sundays from 1:30 p.m. to 10:00 p.m., weather and conditions permitting. Visit www.vta.org for trip planning assistance or contact VTA Customer Service at (408) 321-2300, TTY (408) 321-2330. Follow us on Twitter: @VTA and “Like” us on facebook.com/VTA!

Who: Join Rod Diridon, members of the California Trolley and Railroad Corporation, and the talented volunteers who were vital to the restoration process on a historic trolley ride to downtown San Jose.  Learn about the spirited efforts that led to the funding and restoration of six vintage streetcars.

The California Trolley and Railroad Corporation is a private, non-profit organization with a Board of Directors composed of local business and community leaders founded in 1982.  The restoration effort was made possible through donations from the community and over 90,000 volunteer hours by more than 300 volunteers.  Each car took over one year of full-time volunteer work to be completely restored.  Old parts were saved when possible, and new parts were designed and built when necessary.  Special attention was paid to the historic characteristics of cars which have undergone many changes during their lifetimes. When fully restored, the cars are better than new, with hand-polished wood interiors and fresh coats of brightly colored paint.

CTRC Attendees will need to gather at the Civic Center Light Rail Station (parking at County/former City Hall building) to catch the first loop that begins at 6:18p, arriving at the Diridon Station at 6:38p; the trolley heads back to Civic Center at 6:46p and arrives at 7:04p.  The trolley runs every hour so if attendees want to stay downtown to have dinner or go to Christmas in the Park, they certainly can!

Since we have already promoted the start of “Holly Trolley” service, this opportunity would focus more on the history and volunteer effort (different spin in the media).  Members of the public would have a chance to meet volunteers, learn about the history either while gathered on the light rail platform or in the trolley itself when making its way downtown since you will have a captive audience.  I can distribute a news release and stakeholder update on Wednesday announcing the inaugural ride and include more detailed information about the restoration efforts.

 
<< Start < Prev 1 2 3 4 5 6 7 8 9 10 Next > End >>

Page 1 of 10

Sponsored Links